Home » Project profiles » Stanton Cross

Stanton Cross

Location:Wellingborough, Stanton Cross
Client:Galliford Try
Value:£3m
Duration:2 years across 2 phases
Quantity:
  • 40,000m3 earthworks with 40,000m3 additional ongoing
  • 600 meters of kerb drainage
  • 1000 meters of general site drainage works
  • 2000m of kerbing and road preparation
  • 4500m of edging and footway preparation
  • Installation of 25m x 15m x 6m cofferdam for a holding tank
  • Service crossings
  • Bank Protection works
Overview:

Barton were contracted by Galliford Try to provide an earthworks and civils package for large scale housing, school and residential development for Bovis Homes.

Scope of work:

Barton were contracted by Galliford Try to provide an earthworks and civils package for large scale housing, school and residential development for Bovis Homes.

4000 meters of kerb edging have been laid onsite to date, including storm drains ranging from 900mm to 150mm at various depths, drainage gulley’s and footways. Soft landscaping of onsite soil was also undertaken with further work on a retaining wall to follow.

The site is under development from Bovis Homes, with an expected 3.650 homes, employment areas and shopping facilities planned across the site to rejuvenate Wellingborough.