Swindon earthworks for Gazeley | B&Q Warehouse

Date: Category: Barton News

The Barton team have successfully moved 78,000m3 of surcharge material at Swindon site, to prepare a platform for a new warehouse for Gazeley and their client B&Q.

The material was won from borrow pits on the site totalling a volume of 88,000m3, to generate the material for the cut and fill earthworks operation and the surcharge. The team are happy with the progress being made onsite, the bout of good weather has kept the project on schedule.